Hi Guys
We just have finished our PCI, no major defect. Most of them are paint touchup and few window frame and glasses are scratched. Our private inspector also pick few incompleted and poor quality work like no seal on top n bottom of the main entrance door and laundry door, poor quality render work and crack on few places on render, few places grouting is not completed.
Handover will be two weeks after PCI. Finger crossed, everything will be as per plan.
Regards!
Tuesday, May 04, 2010
Friday, March 19, 2010
Monday, March 01, 2010
Just waiting for the PCI!!!!!
Sunday, January 31, 2010
Tuesday, January 19, 2010
January Updates!!!!!
Hi Guys
As from 22-Dec-2009 to 26-01-10 is the industry shutdown period. We don't have much update.
We have few updates-
:: Skirting & Architrave done
:: Waterproofing done
:: Tiles in wet areas done
:: Painting started
Regards
As from 22-Dec-2009 to 26-01-10 is the industry shutdown period. We don't have much update.
We have few updates-
:: Skirting & Architrave done
:: Waterproofing done
:: Tiles in wet areas done
:: Painting started
Regards
Monday, December 14, 2009
December Updates!
Two weeks earlier Tyrells conducted the independent inspection. As per our SS, there is no major issue. Both Local and Tyrells inspections passed.
We have few updates!
:: Doors & Skirting Delivered & Installed
:: Kitchen & Vanities Supplied
:: Stairs Installed
:: Gyprocks Installed